The following proposals have been developed and brought forward for decision under delegated authority granted to the Combined Authority’s Chief Executive in consultation with the Chief Executives of the Combined Authority’s constituent councils:

a. The Full Business Case for the Thornbury Hospital Site and award of £3.806m via the Land Acquisition Fund which will be repaid fully by March 2025.

b. A Change Request for the Mass Transit project: To approve an additional £37k funding for Mass Transit accommodated with the ‘tail’ for that project.

c. The Feasibility and Development Funding Application Form for the Bus Service Improvement Plan/Enhanced Partnership and award of £537k.

Appendix 1 sets out further background detail.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 04/10/2021

Decision due: 16 Sep 2021 by Chief Executive, West of England Combined Authority

Contact: Patricia Greer, CEO Email: patricia.greer@westofengland-ca.gov.uk.

Consultation process

The Chief Executives of the Combined Authority’s constituent councils were consulted on this proposal.