Decisions

Use the below search options at the bottom of the page to find information regarding recent decisions that have been taken by the Combined Authority’s decision making bodies.

Alternatively you can visit the officer decisions page for information on officer delegated decisions that have been taken by West of England Combined Authority officers.

Decisions published

23/04/2024 - Skills Bootcamp Growth W4 and Carry Over Contracts W5 ref: 632    Recommendations Approved

Decision Maker: Strategic Director of Economy & Skills

Decision published: 08/05/2024

Effective from: 23/04/2024

Decision:

That Directors:-

 

1)    Approved the carry over contracts for 7 providers and 9 projects, with a total amount of £1,857,379.61, this total is across all 9 projects.

2)      Approved the growth funding for £306,036.44 for 6 projects.

 


23/04/2024 - Carry Over Contracts and Growth Funding Multiply ref: 631    Recommendations Approved

Decision Maker: Strategic Director of Economy & Skills

Decision published: 08/05/2024

Effective from: 23/04/2024

Decision:

That:

The Directors

 

1)    Approved the extending the contracts of existing Multiply providers who have met their KPIs. 

 

2)    Approved the use underspend to allocate growth funding to one further Multiply provider. 

 


26/04/2024 - Adult Education Budget (AEB) 2022-23 reconciliation and recovery of funds ref: 628    Recommendations Approved

Decision Maker: Strategic Director of Economy & Skills

Decision published: 01/05/2024

Effective from: 26/04/2024

Decision:

Decision Taken

 

That the West of England Mayoral Combined Authority Strategic Director of Economy and Skills approves:

 

1)    That £1,498,260 is recovered from 10 providers (4 of whom no longer hold grants in the 2023/24 academic year). This includes £686,237 of National Skills Fund Level 3 (NSF L3) / Free Courses for Jobs (FCFJ) funding.

 

2)    That £357,334 is protected and not recovered following the assessment of payment protection requests received and due to over delivery in other priority categories.

 


26/04/2024 - Adult Education Budget (AEB) 2022/23 Audit & Assurance Review Outcomes ref: 625    Recommendations Approved

Decision Maker: Strategic Director of Economy & Skills

Decision published: 01/05/2024

Effective from: 26/04/2024

Decision:

Decision Taken

 

That the West of England Mayoral Combined Authority Strategic Director of Economy and Skills approves:

 

1)    That partial recovery is undertaken to clawback the actual value of outstanding errors only.

 

2)    That any eligible over delivery is utilised to minimise the amount of clawback required.

 


26/04/2024 - Adult Education Budget (AEB) Adult Skills Fund (ASF) commissioning plan and curriculum delivery plan process for 2024-25 academic year ref: 629    Recommendations Approved

Decision Maker: Strategic Director of Economy & Skills

Decision published: 01/05/2024

Effective from: 26/04/2024

Decision:

Decision Taken

 

That the West of England Mayoral Combined Authority’s Strategic Director of Economy and Skills agrees:

1)    The West of England Mayoral Combined Authority Adult Skills Fund Commissioning Plan for the 2024/25 academic year.

2)    The Curriculum Delivery Plan (CPD) process for agreeing CPD with each provider, and confirming the due diligence is met satisfactorily prior to awarding an allocation and issuing the Grant Funding Agreement.

 


22/04/2024 - Low Carbon Business Support - Green Business Grants ref: 618    Recommendations Approved

Decision Maker: Director of Environment

Decision published: 29/04/2024

Effective from: 22/04/2024

Decision:

That £10,972.95 of grant is awarded to 3 applicants. If all are awarded, this will leave:

 

  • £1.75m remaining of the £2.0m total Green Business Grants pot to allocate
  • £234k remaining of the £500k total Rooftop Solar Grants pot to allocate.
  • £198k remaining of the £198k total Heat Pump Grants pot to allocate

 

Ref

Company

Improvement

Grant sought

Green Business Grants

GBG422-2

John Perkins Construction Ltd

LED lighting

£1,426.51

GBG541

John Sheppard Butchers Ltd

High speed shutter door

£3,632.00

GBG672

Mitchell & Co Building Services Ltd

Solar photovoltaic panels

LED lighting

£5,914.44

Total

£10,972.95

 


22/04/2024 - Approval of Funding for Nature Recovery Projects (Green Recovery Fund Round 2) ref: 619    Recommendations Approved

Decision Maker: Director of Environment

Decision published: 29/04/2024

Effective from: 22/04/2024

Decision:

That £1,244,947 from the £2.3m of Green Recovery Fund earmarked for Nature Recovery is allocated to the following projects:

 

·         Bathscape Landscape City Framework: £225,827. Led by Bath & North East Somerset

·         Managing More Greenspace for Nature: £649,120. Led by Bristol City Council

·         Linking the Levels: £370,000. Led by South Gloucestershire Council

 


17/04/2024 - Safer Shops West Grant Award & Project Change Request ref: 617    Recommendations Approved

Decision Maker: Chief Executive, West of England Combined Authority

Decision published: 24/04/2024

Effective from: 17/04/2024

Decision:

That the West of England Combined Authority Interim Chief Executive Officer in consultation with the West of England Local Authority Chief Executive Officers, approve the following:

 

1)    Award of three Safer Shop West grant fund applications, totaling £4,971.

2)    Extend the project delivery schedule by six months, closing in October 2024.

3)    Reprofiling of the project budget.

4)    Increase the maximum grant level to £4,000 and reduce the business match to 20%.

 


26/10/2023 - CRSTS - Thornbury to North Bristol Corridor (A38N) ref: 615    Recommendations Approved

Decision Maker: Strategic Director of Infrastructure

Decision published: 23/04/2024

Effective from: 26/10/2023

Decision:

To approve change request and the award of £500k from CRSTS capital to South Gloucestershire Council for the CRSTS Thornbury to North Bristol Corridor (A38N) project to enable the project to conduct ground radar surveys within this financial year.


26/10/2023 - CRSTS - Chipping Sodbury to Hambrook Corridor (A4174/A432) ref: 616    Recommendations Approved

Decision Maker: Strategic Director of Infrastructure

Decision published: 23/04/2024

Effective from: 26/10/2023

Decision:

To approve change request and the award of £400k from CRSTS capital to South Gloucestershire Council for the CRSTS - Chipping Sodbury to Hambrook Corridor (A4174/A432) project to enable the project to conduct ground radar surveys within this financial year.


11/04/2024 - Grant Funding Agreement with Bristol City Council to deliver RIBA 1-3 Temple Quarter - Northern Entrance and Southern Gateway ref: 614    Recommendations Approved

Decision Maker: Strategic Director of Infrastructure

Decision published: 17/04/2024

Effective from: 11/04/2024

Decision:

That:

 

1)    The West of England Combined Authority enters into a grant funding agreement with Bristol City Council to deliver the ‘Temple Quarter – Northern Entrance and Southern Gateway’ scheme as part of the Phase 1 works funded from the successful, Homes England (HE) Brownfield Investment Land (BIL) Grant

 

2)    The West of England Combined Authority, as accountable body, allocates funding of £5,223,034 of the BIL grant to fund *RIBA stages 1-3 of the Northern Entrance and Southern Gateway projects, in accordance with the ‘Request for Allocation of Funding’ received from Bristol City Council, and the grant funding agreement to be entered into per decision 1) above.

 

*Royal Institute of British Architects Plan of Work Stages 1 to 3

 


01/07/2022 - Joint Committee Governance Review ref: 613    Recommendations Approved

Decision Maker: West of England Joint Committee

Made at meeting: 01/07/2022 - West of England Joint Committee

Decision published: 16/04/2024

Effective from: 01/07/2022

Decision:

This item was deferred to a future meeting


01/07/2022 - LEP & IBB Budget Outturn April-March 2022 ref: 612    Recommendations Approved

Decision Maker: West of England Joint Committee

Made at meeting: 01/07/2022 - West of England Joint Committee

Decision published: 16/04/2024

Effective from: 01/07/2022

Decision:

The Joint Committee RESOLVED:

 

1) To note the Revised Analysis of LEP External Grants as at the end of March 2022 as set out in Figure 1;

 

2) To note the LEP revenue outturn as set out in Appendix 1;

 

3) To approve the Full Business Case for the Thornbury High Street project and the award of £4.557m through the Economic Development Fund.

 

4) To approve the change requests for schemes in the Local Growth and Getting Building Fund programme as set out in Appendix 2;

 

5) To approve the change requests for schemes in the Economic Development and Revolving Infrastructure Fund programmes as set out in Appendix 3.