Decision details
To seek approval of the A4 Portway Strategic Corridor change request
Decision Maker: Strategic Director of Infrastructure
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
There are two main reasons necessitating the change these are
1.This Portway Park & Ride
bus access/egress package of works has the potential to be
deliverable much sooner than the measures in the wider A4 Portway
Strategic Corridor project and deliver outcomes / benefits that
meet the objectives for CRSTS.
2.There is a time pressure to deliver this element on an accelerated timeline based on the agreed transport mitigations for the YTL Arena. YTL are planning on running event buses from the Portway Park and Ride site along the M5 to the Arena at the Brabazon Hangar. The agreement with YTL states that all travel mitigations will be in place prior to the Arena opening at the end of 2024. If left included as part of the strategic corridor Outline Business Case (OBC), it is unlikely that the new bus access / egress would be delivered in time for this deadline.
Decision:
Approval of the change in scope to progress Portway P&R bus access improvement work package as separate Full Business Case to be completed by n May 2023 with additional funding of £170,393 through CRSTS
Approval of the change in programme for the A4 Portway Strategic Corridor Outline Business Case to be completed by October 2023 with additional funding of £458,986
Reasons for the decision:
There are two main reasons necessitating the change these are
1.This Portway Park & Ride bus access/egress package of works has the potential to be deliverable much sooner than the measures in the wider A4 Portway Strategic Corridor project and deliver outcomes / benefits that meet the objectives for CRSTS.
2.There is a time pressure to deliver this element on an accelerated timeline based on the agreed transport mitigations for the YTL Arena. YTL are planning on running event buses from the Portway Park and Ride site along the M5 to the Arena at the Brabazon Hangar. The agreement with YTL states that all travel mitigations will be in place prior to the Arena opening at the end of 2024. If left included as part of the strategic corridor Outline Business Case (OBC), it is unlikely that the new bus access / egress would be delivered in time for this deadline.
Alternative options considered:
An alternative option considered was to allow Portway P&R bus access / egress to be delivered at a later date, as part of the overall Portway project. However, this option does not meet the agreed transport mitigations for the YTL Arena
Publication date: 11/05/2023
Date of decision: 30/03/2023
Accompanying Documents: