Decision details
Investment Fund delegated decisions
Decision Maker: Chief Executive, West of England Combined Authority
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The following proposals have been developed
and brought forward for decision under delegated authority granted
to the Combined Authority’s Chief Executive in consultation
with the Chief Executives of the Combined Authority’s
constituent councils:
a. The Full Business Case for the Thornbury Hospital Site and award
of £3.806m via the Land Acquisition Fund which will be repaid
fully by March 2025.
b. A Change Request for the Mass Transit project: To approve an
additional £37k funding for Mass Transit accommodated with
the ‘tail’ for that project.
c. The Feasibility and Development Funding Application Form for the
Bus Service Improvement Plan/Enhanced Partnership and award of
£537k.
Appendix 1 sets out further background detail.
Decision:
1. To approve the Full Business Case for the
Former Hospital Site Thornbury and award of £3.806m via the
Land Acquisition Fund which will be repaid fully by March
2025.
2. To approve an additional £37k funding for Mass Transit
accommodated with the ‘tail’ for that project.
3. To approve the Bus Service Improvement Plan Feasibility and
Development Funding Application Form and award of
£537k.
Alternative options considered:
Not applicable in relation to this specific
decision, i.e. this was the option considered.
Publication date: 04/10/2021
Date of decision: 16/09/2021