Local Growth Fund, Getting Building Fund and Economic Development Fund change requests
Decision Maker: Chief Executive, West of England Combined Authority
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
There is a requirement that all Local Growth
Fund (LGF) grant funds are spent by March 2021 and also a condition
that the Getting Building Fund (GBF) is spent within the financial
year it was awarded, that being £6.85m in 2020/21 and
£6.85m in 2021/22.
Owing to the need to manage scheme changes, including any necessary
funding swops to ensure full grant spend, in advance of the next
WECA / Joint Committee meeting, the following delegations to the
WECA Chief Executive in consultation with the West of England Chief
Executives were granted at the 29 January 2021 meeting of the WECA
/ Joint Committee:
- Approval of changes to funding profile and programme for schemes
within the current LGF, GBF, Economic Development Fund and
Revolving Infrastructure Fund programmes
- Approval of the reallocation of funding for schemes in the
approved LGF/GBF programme including swops with the EDF, and
exceptionally the Investment Fund.
A number of recommended changes to schemes within the current Local
Growth Fund / Getting Building Fund and Economic Development Fund
programme were subsequently identified for approval. The key
changes were:
Local Growth and Getting Building Funds:
*The Emersons Green Local Transport Enhancements, Umbrella and the
South Gloucestershire Sustainable Transport Package projects
jointly report reprofiling of £2.614m of LGF/GBF to 2021/22.
In order to meet LGF spend profiles, it was proposed to swop these
funds with EDF for the Cribbs Patchway MetroBus Extension. Approval
at this time will enable this to be picked up in the Quarter 3
grant claim.
*The Emersons Green Local Transport Enhancements and Umbrella
projects are also in the GBF programme. Whilst this has an end date
of 2021/22, given the requirement to spend half the programme award
this year, this change has necessitated a request to MHCLG for the
inclusion of an additional project in the GBF programme, that being
the Bath Quays North Infrastructure Development Works. It should be
noted that these changes do not alter the overall funding awarded
to these projects, just the funding blend.
The Chief Executives of the West of England unitary authorities
were consulted on these proposals and were in agreement with the
decision.
Decision:
Approval given to recommended changes to
schemes within the current Local Growth Fund / Getting Building
Fund and Economic Development Fund programme as follows:
Local Growth Fund / Getting Building Fund:
- Emersons Green Local Transport Enhancements
Milestones: 2-6 month slippage for 6 milestones including
completion (to Nov 2021).
Spend: Swop of £1.913m of LGF for EDF with the Cribbs
Patchway MetroBus Extension receiving the LGF [Revised LGF/GBF
total £3.137, profiled £918K in 20/21 and £1.318m
in 21/22, EDF total £1.913m profiled in 21/22]
- South Gloucestershire Sustainable Transport Package
Spend: Swop of £551k of LGF for EDF with the Cribbs Patchway
MetroBus Extension receiving the LGF [Revised LGF total
£2.244m and EDF £551K profiled in 21/22]
Scope: Reallocation of funding between package elements
- Umbrella: Swop a total of £150k of LGF for EDF with the
Cribbs Patchway MetroBus Extension receiving the LGF [Revised
LGF/GBF total £3.332m and EDF total £353k profiled in
21/22]
- Cribbs Patchway MetroBus Extension: Swop a total of £2.614m
of EDF for LGF with the South Gloucestershire Sustainable Transport
Package (£551k), Emersons Green Local Transport Enhancements
(£1.913m) and UMBRELLA project (£150k) [Revised LGF
total £9.979m and EDF total £25.021m profiled
£2.852m in 20/21, £13.84m in 21/22, £5.992m in
22/23 and £1.48m in 23/24]
- Bath Quays North Infrastructure Development Works: The
reprofiling of spend for Emersons Green Local Transport
Enhancements and Umbrella above has reduced forecast GBF spend
overall below the 20/21 award. It is therefore proposed to add this
additional project to the GBF programme subject to sign off by
MHCLG. This project would receive GBF instead of LGF.
Economic Development Fund
- Avonmouth Severnside Ecology Mitigation and Flood Defences:
reprofiling £5.557m into 22/23, 23/24 and 24/25. [Revised EDF
total £63.9m, profiled £9.605m in 20/21, £12.935m
in 21/22, £11.652m in 22/23, £8.18m in 23/24 and
£17.151m in 24/25]
Alternative options considered:
Not applicable in relation to this specific
decision, i.e. this was the option considered.
Publication date: 03/03/2021
Date of decision: 18/02/2021
Accompanying Documents: